The Flexible Engineering Building 64/5 on the Daimler AG factory premises in Sindelfingen, Germany

NEW CONSTRUCTION OF AN OFFICE BUILDING (HIGH-RISE)

Construction project: New office building (high-rise), building 64/5 & EK 847

Project period: 11/16 to 08/20

Flats:

  • GFA 11,795 m²
  • BRI 46,409.16 m³

Total investment: € 24.90 million  Costs for building services: €7.72 million

Functional areas: 550 office workstations, foyer, technical centre, meeting rooms

Scope: Plant groups 1 to 8

Work phases: 1 – 8 HOAI

Planning: 3D planning

Special equipment: Heating/cooling ceiling, smoke pressure systems for fire brigade elevator and staircase, power supply via transformer in the building, daylight and presence-dependent lighting control, energy duct, office concept.

Information on sustainability, EnEv: RELM criteria catalogue of Mercedes-Benz AG

Client
Daimler AG
Date
January 10, 2020
Our Role
Art Direction, UI/UX, Construction